CBI Community Bridges Inc
No existing concrete
(Laying out the measurements)
Tree Root
Pulled out with jack and Ford F350
PCV for generator cables
Stem Wall
Stem-wall and Slab Edge
Completed
(Inside View)
Completed
(Outside View)
Completed
(Gate View)
Interesting Facts About The Project
We had to remove a substantial tree root. We first placed a bottle jack under the root and raised it out as much as the bottle jack was able to. Then we tied a chain to the root and an Ford F350 and yanked it out.
This structure was built to house electric backup generators for the CBI mental health facility.